Construction Projects Update:   

Downtown Redevelopment Infrastructure Improvements - Phase IIIC - Project 1

Downtown Redevelopment Infrastructure Improvements - Phase IIIC - Project 2

  • Project start date:  Anticipated to be March 2018
  • Project completion date: Anticipated to be November 2019
  • Project Conceptual Plans
  • Project Bid Date: December 20, 2017
  • Final Addendum #5 to be issued December 14, 2017.

2nd Street North Parking Lot Improvements Project

  • Project start date:  January 30, 2017
  • Project completion date: COC issued on December 1, 2017
  • Construction Project Information Flyer
  • Project 99% complete
  • Awaiting Final As-built submittals and completion of punch list items.

Miscellaneous Water Main Replacement Project - Phase D

  • Project start date:  June 5, 2017
  • Project completion date: November 2, 2017
  • Construction Project Information Flyer
  • Project 99% complete
  • Awaiting Final As-Built submittals and completion of punch list items.
  • Also awaiting cost proposal from contractor for additional work within Constitution Cove subdivision.

Hopson Road Infrastructure Improvements Project

  • Project start date:  October 30, 2017
  • Project completion date: March 31, 2018
  • Construction Project Information Flyer
  • 7% of Gravity Sewer work completed as of 12/14/17.
  • 15% of Water Main work completed as of 12/14/17.

Contact Information

1460-A Shetter Avenue
Second Floor
Jacksonville Beach, FL 32250

Ph: (904) 247-6219
After-Hours and Emergencies:
Ph: (904) 247-6278
Fax: (904) 247-6117
Contact Us

Hours
7:00 am - 4:00 pm
Monday - Friday

 

Road Closures:  

There are currently no road closures.

 

 

 

 

 

 

 

Search form