Construction Projects Monthly Update as of June 2013
- PROJECT: Downtown Vision Plan Project
- PROJECT: 2nd Street North Sewer & Related Improvements Project
- Area: 2nd Street N. - 14th to 20th Avenues
- Start: 1/2013
- Estimated Completion: 2/2014
- Current Percent Complete: 25%
- Comments: Phase 1 construction underway. (See phasing map)
|