Construction Projects / Road Closure Updates

Lift Station Number 2 Replacement Project

  • Project start/end dates
    • Item 1: January 4, 2021 / April 16, 2021
    • Item 2: March 15, 2021 / October 1, 2021
  • Project Flyer (PDF)

Lift Station Number 17 & 23 Rehabilitation Site Upgrades Part A & B Project

  • Project start/end dates
    • Part A: January 25, 2021 / May 24, 2021
    • Part B: May 24, 2021 / June 18, 2021
  • Project Flyer (PDF)

Jacksonville Beach Water & Sewer Improvements

  • Item 1 - 99% complete as of April 8, 2021
  • Item 2 - Project start date: April 21, 2021
  • Item 3 - Tentative project start date: May 24, 2021
  • Item 4 - 99% complete as of April 2, 2021 
  • Project Flyer (PDF)
  • The City's Rights-of-Way known as 10th Avenue South Street End will be temporarily closed for the purpose of facilitating the construction of  an ocean front 5-unit condominium at 22 10th Avenue South.  The Temporary Construction Use Permit expires on September 30, 2022.   The sidewalk and beach crosswalk will remain open .